Home About Us Representative Projects Services Office Locations Career Opportunities News & Links Contact Us

 

 

BROWN STATION ROAD LANDFILL - New Generating Facility
Prince George's County, MD

Brown Station Road Landfill New Co-Generating Facility is a 4-megawatt generating facility at the Brown Station Road Landfill in Prince George's County, MD. It serves as a means to convert the harmful and polluting gas (methane) that is produced by the landfill into a valuable resource, electricity. It consists of 4 one-megawatt generators, which run on the landfill gas. The electricity produced by the generators powers the plant, which requires approximately 800KW to run. The excess electricity, 3.2 MW, is exported to the local utility, PEPCO.

The building is a 5710 s.f. structure of steel and masonry construction. The majority of the building is the 47' X 80' engine room with a ceiling height of 20', which houses the generators. The rest of the building serves to support the generator operations and include the state of the art control room, the switchgear room and a conference room. The exterior finish is a custom order 12" fluted block. There were approximately 6700 block used and each block weighs 60 pounds. Site work included replacement of 500 feet of the gas pipeline to serve the gas supply to the correctional facility, a new parking lot, landscaping and a bio-retention pond.

Each of the four generators has a 1500HP, twelve-cylinder engine with 7040 cu. in. displacement. They produce 1,000,000 watts of power at 4,160 volts. They consume approximately 350 cubic feet of the landfill gas per minute. They are 15 feet long, 7 feet wide and nine feet high and weigh 37,500 pounds. The generator units are placed on individual inertia packs.

The generators are connected to a 5kv switchgear lineup. This 7-section switchgear parallels the generators together. It also distributes power to the building via a 2000KVA 4160 to 480V transformer. Power is exported to PEPCO via a 7500KVA 4160 to 13,750 volt transformer and a 15KV switchgear outdoor lineup installed in a new stand alone structure.

In addition to the construction of the new generator building and installation of the new generators, the project consisted of completely gutting and renovating the existing compressor building, which processes the gas into burnable fuel for the generators. As part of this renovation four gas-powered compressors were removed and replaced by three electrically driven compressors. A new process chiller and filtering system were also installed in the compressor building upgrade. The capacity of gas that can be processed was increased by 225% by the upgrades. As well as providing gas to the new generators, the compressor building supplies gas to three existing generators and boilers at a correctional facility two miles from the landfill. The existing system serving the correctional facility has been in operation since 1986.

The gas is extracted from the hill by an extensive array of wells connected to a common pipeline header. In the first step in the process the gas header enters a knockout tank. As it enters some of the moisture and contaminants are dropped out. The gas then passes through a series of entrainment separators to the compressors. The compressors compress the gas to 80 PSI. In this process the gas is heated to approximately 100 degrees F. The compressed and heated gas is then cooled to 40 degrees. The cooling process causes the major amount of moisture to condense. The cooled gas passes through a battery of gas scrubbers, filters, and dryers. These remove the condensation along with most of the others contaminants. The clean and dry gas is then ready to be utilized as fuel for the generators and boilers. All of the piping and processing equipment are made of stainless steel to be able to withstand the corrosive properties of the gas passing through it.

The complete plant operation, power generation and gas processing is fully automated by a PLC based control system and data acquisition system. Compressors will automatically come up or shutdown to maintain desired capacity dependent on the demand of the generators and boilers. The generator will load and unload to maintain a steady level of exported power, selected by the user, or to maintain a specified number of generators to maintain online status. The plant is designed to run continuously 24/7. To ensure safety of the operation, plant control is interlocked to the fire alarm system, a methane gas detection system and oxygen level in the gas. The presence of any of these conditions will automatically shutdown the plant. The automation system also monitors gas pressures above acceptable tolerances, temperatures, flow rates and moisture throughout the processing. The generators are monitored for engine oil temperature and pressure, jacket water temperature, cylinder and exhaust temperatures, as well power output; KW, KWH voltage and frequency. The power usage and product at the remote location of the correctional facility are also monitored. The operational status of the primary building functions of the flare building, another remote location, are monitored by the new DAS system. The building ventilation is also controlled automatically for temperature as well as combustion air for the generators.

To make this automation system functional, 34,000 feet of control cable were run using a distribution system that included cable tray and conduit. 2200 control point terminations were made. All of this in an area of less than 8500 square feet.

The project was challenging in many regards including integrating software and hardware systems that have not been utilized together previously. The intent of the project was clear, however the successful completion required extensive modification and fine tuning throughout the construction process to achieve the end result.

 

 

 
Home | About Us | Representative Projects | Services | Office Locations | Career Opportunities | News & Links | Contact Us
 
 
Corporate Headquarters  ||  220 8th Avenue NW  |  Glen Burnie, MD 21061  |  V. 410.412.2100  |  F. 410.412.2102
 
©2004, Primo Electric Company
Primo Electric Company IES